位置:首页 > 题库频道 > 其它分类 > 计算机其它 > 专业技术高级资格信息系统项目管理师综合知识2006年下半年信息系统项目管理师上午试卷

● Project (69) Management includes the processes required to ensure thatthe project includes all the work required, and only the work required, tocomplete the project successfully.

发布时间:2024-07-09

A.Integration

B.Scope

C.Configuration

D.Requirement

试卷相关题目

  • 1● In the project management context, (68) includes characteristics ofunification, consolidation, articulation, and integrative actions that arecrucial to project completion, successfully meeting customer and otherstakeholder requirements, and managing expectations.

    A.integration

    B.scope

    C.process

    D.charter

    开始考试点击查看答案
  • 2● Organizations perform work to achieve a set of objectives. Generally,work can be categorized as either projects or operations, although the twosometimes are (67) .

    A.confused

    B.same

    C.overlap

    D.dissever

    开始考试点击查看答案
  • 3● (66) from one phase are usually reviewed for completeness and accuracyand approved before work starts on the next phase.

    A.Process

    B.Milestone

    C.Work

    D.Deliverables

    开始考试点击查看答案
  • 4● 下列不能作为监理依据的是(65) .

    A.现行国家,各省,市,自治区的有关法律,法规

    B.国际,国家IT行业质量标准

    C.业主单位和承建单位的合同

    D.承建单位的指令

    开始考试点击查看答案
  • 5● 业主单位授予监理单位的权力,应明确反映在(64) 中,据此项目监理机构才能开展监理活动.

    A.监理合同

    B.监理大纲

    C.监理规划

    D.监理计划

    开始考试点击查看答案
  • 6● On some projects, especially ones of smaller scope, activity sequencing,activity resource estimating, activity duration estimating, and (70) are sotightly linked that they are viewed as a single process that can be performedby a person over a relatively short period of time.

    A.time estimating

    B.cost estimating

    C.project planning

    D.schedule development

    开始考试点击查看答案
  • 7● In approximating costs, the estimator considers the possible causes ofvariation of the cost estimates, including(71) .

    A.budget

    B.plan

    C.risk

    D.contract

    开始考试点击查看答案
  • 8● Project Quality Management must address the management of the projectand the (72) of the project. While Project Quality Management applies to allprojects, regardless of the nature of their product, product quality measuresand techniques are specific to the particular type of product produced by theproject.

    A.performance

    B.process

    C.product

    D.object

    开始考试点击查看答案
  • 9● (73) is a category assigned to products or services having the samefunctional use but different technical characteristics. It is not same asquality.

    A.Problem

    B.Grade

    C.Risk

    D.Defect

    开始考试点击查看答案
  • 10● Project (74) Management is the Knowledge Area that employs theprocesses required to ensure timely and appropriate generation, collection,distribution, storage, retrieval, and ultimate disposition of projectinformation.

    A.Integration

    B.Time

    C.Planning

    D.Communication

    开始考试点击查看答案