● Schedule development can require the review and revision of duration estimates andresource estimates to create an approved(74)that can serve as a baseline to track progress.
A.scope statement
B.activity list
C.project charter
D.project schedule
试卷相关题目
- 1● (73) is a method used in Critical Path Methodology for constructing a projectschedule network diagram that uses boxes or rectangles, referred to as nodes, to representactivities and connects them with arrows that show the logical relationships that exist betweenthem.
A.PERT
B.AOA
C.WBS
D.PDM
开始考试点击查看答案 - 2● The project life-cycle can be described as(72).
A.project concept, project planning, project execution, and project close-out
B.project planning, work authorization, and project reporting
C.project planning, project control, project definition, WBS development, andproject termination
D.project concept, project execution, and project reporting
开始考试点击查看答案 - 3● Risk management allows the project manager and the project team not to(71).
A.eliminate most risks during the planning phase of the project
B.identify project risks
C.identify impacts of various risks
D.plan suitable responses
开始考试点击查看答案 - 4● 在项目质量监控过程中,在完成每个模块编码工作之后就要做的必要测试,称为(70)。
A.单元测试
B.综合测试
C.集成测试
D.系统测试
开始考试点击查看答案 - 5● 质量管理六西格玛标准的优越之处不包括(69)。
A.从结果中检验控制质量
B.减少了检控质量的步骤
C.培养了员工的质量意识
D.减少了由于质量问题带来的返工成本
开始考试点击查看答案 - 6● The Develop Project Management Plan Process includes the actions necessary todefine, prepare, integrate, and coordinate all constituent plans into a (75)
A.Project Scope Statement
B.Project Management Plan
C.Forecasts
D.Project Charter
开始考试点击查看答案
最新试卷
注册安全工程师注册安全工程师安全生产法及相关法律知识国家
类别:建筑类其它注册安全工程师注册安全工程师安全生产法及相关法律知识2019
类别:建筑类其它注册安全工程师注册安全工程师安全生产法及相关法律知识2018
类别:建筑类其它注册安全工程师注册安全工程师安全生产法及相关法律知识2018
类别:建筑类其它注册安全工程师注册安全工程师安全生产法及相关法律知识2018
类别:建筑类其它注册安全工程师注册安全工程师安全生产法及相关法律知识2014
类别:建筑类其它注册安全工程师注册安全工程师安全生产法及相关法律知识2014
类别:建筑类其它注册安全工程师注册安全工程师安全生产法及相关法律知识2014
类别:建筑类其它注册安全工程师注册安全工程师安全生产法及相关法律知识2014
类别:建筑类其它注册安全工程师注册安全工程师安全生产法及相关法律知识2014
类别:建筑类其它