位置:首页 > 题库频道 > 其它分类 > 资格类其它 > 项目管理师PMP美国项目管理PMPPMP认证考试练习题(7.8)

which of the following actions is an example of risk response:

发布时间:2024-07-09

A.adjust project parameters (scope, time, quality ...)

B.reduce the probability of potential project risk events

C.reduce the consequences of potential project risk events

D.wait until a problem actually happens, then deal with it in the most effective and efficient manner.

E.a, b and c only

试卷相关题目

  • 1the logical relationship that communicates a delay between the start/finish of one activity and the start/finish of another activity is referred toas:

    A.slack

    B.free float.

    C.restricted float.

    D.level float.

    E.lag

    开始考试点击查看答案
  • 2the "buy or make" decision is usually made during the:

    A.acquisition cycle

    B.contract evaluation cycle

    C.requirements cycle

    D.pre-award cycle

    E.at any time that is convenient for the project manager

    开始考试点击查看答案
  • 3most quality problems:

    A.originate in the quality department where the ultimate responsibility for quality rests.

    B.originate on the shop floor because of waste and product rework.

    C.are the results of management inattention to potential quality improvement ideas.

    D.could be eliminated if shop supervisors monitored their work more closely.

    E.a and b

    开始考试点击查看答案
  • 4it is argumentative whether project managers actually control costs. which of the following is the most common element over which theproject manager may have some degree of control、

    A.direct labor dollars

    B.direct labor hours.

    C.overhead rates.

    D.procurement costs.

    E.none of the above.

    开始考试点击查看答案
  • 5including the customer in the process of project planning is:

    A.slow and counterproductive.

    B.essential in the definition and documentation of project goals.

    C.necessary, but of limited value.

    D.unnecessary because project goals are defined in the proposal stag

    E.E.none of the above.

    开始考试点击查看答案
  • 6a comparison of completion status to baseline is referred to as (    ).

    A.earned value measurement.

    B.percent complete.

    C.acwp.

    D.bcws

    E.none of above.

    开始考试点击查看答案
  • 7an example of coercive power would be:

    A.demotion

    B.reduction in wages

    C.disciplinary layoff

    D.reprimand

    E.all of the above

    开始考试点击查看答案
  • 8job descriptions are examples of (    )communications.

    A.upward

    B.downward

    C.horizontal

    D.diagonal

    E.none of the above

    开始考试点击查看答案
  • 9monte carlo simulation:

    A.was originally developed by dr. carlo

    B.is a european technique for assessing project risks

    C.assumes the future risk events will occur at random according to predetermined probability distributions

    D.is a technique to stimulate create risk event resolution

    E.a, b and c only

    开始考试点击查看答案
  • 10the pareto principle is a technique used to determine which quality control problems in a particular process should be corrected. which ofthe following statements best represents the philosophy employed by this principle、

    A.in order to minimize financial losses from quality control problems, all problems which have a measureable cost should be corrected

    B.the majority of defects are caused by a small percentage of the identifiable problems. improvement efforts should be reserved for these vitalproblems.

    C.in order to achieve zero defects, all quality control problems, including those which do not have a direct financial cost should be correcte

    D.D.generally, 80% of the quality control problems are justifiable for correction via cost-benefit analysis. the remaining 20% are not financiallyworthy of improvement efforts.

    E.a and d

    开始考试点击查看答案
返回顶部