As a project is carried out and slack time is consumed on individual tasks, the slack left over for the remaining tasks is:
A.Insignificant.
B.Reduced.
C.Unchange
D.C.Unchanged.D.Increased.
E.Doubled.
试卷相关题目
- 1Fast tracking means to:
A.Speed up a project through parallel tasks.
B.Swap one task for another.
C.Reduce the number of tasks if possible.
D.B and C.
E.None of the above.
开始考试点击查看答案 - 2The key purpose of project control is to:
A.Plan ahead for uncertainties.
B.Generate status reports.
C.Keep the project on track.
D.Develop the project road map.
E.All of the above.
开始考试点击查看答案 - 3Excessive flexibility in specifying requirements will ( ) the likelihood of time overruns.
A.Reduce.
B.Eliminate.
C.Double
D.Increase
E.Not affect
开始考试点击查看答案 - 4The actual configuration of a PERT/CPM network ( ) the amount of resources that can be devoted to the project.
A.Increases.
B.Is not affected by
C.Does not require
D.Is heavily dependent upon
E.Is the only means of determining
开始考试点击查看答案 - 5All of the following are categories of a milestone in a schedule except:
A.End date.
B.Contract dates.
C.Key events schedule
D.D.Imposed dates.
E.Task duration.
开始考试点击查看答案 - 6The purpose of a dummy activity in an activity-on-arrow diagram is to:
A.Identify a task that could be replaced by another.
B.Take the slack time into account.
C.Show a task that is not necessarily neede
D.D.Denote a mileston
E.E.Show a dependency relationship.
开始考试点击查看答案 - 7On November 1, $1000 worth of work on task A was supposed to have been done (BCWS); however, the BCWP was $850. Calculate the schedule variance:
A.¥-100
B.¥100
C.¥-150
D.¥150
E.85%
开始考试点击查看答案 - 8A plan has budgeted three weeks of effort for consultants, but the job was done in only two weeks. Calculate the variance:
A.1.50%
B.33.00%
C.75%
D.67%
E.None of the above.
开始考试点击查看答案 - 9Resource leveling will often affect the project by making it:
A.Shorter.
B.Longer
C.More responsive to customer needs.
D.A and C.
E.B and C.
开始考试点击查看答案 - 10Using the figure in the Special window, The slacktime in Activity "G" is ( ) weeks.
A.2
B.3
C.4
D.5
E.7
开始考试点击查看答案
最新试卷
房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它