Which of the following impacts the critical path、
A.Changing the task duration.
B.Reduce the free float of an activity.
C.Executing a backward pass
D.A or B.
E.None of the above.
试卷相关题目
- 1The range of time allowed for an activity to be completed in is the ( ).
A.Planned time (Duration).
B.Float time (LS - ES, or LF - EF).
C.Critical time (when ES = LS, or EF = LF).
D.Scheduled time (LF - ES).
E.Event.
开始考试点击查看答案 - 2Free float is the amount of time that an activity may be delayed with out affecting the ( ).
A.Early start of the succeeding activities.
B.Late start of the succeeding activities.
C.Project finish.
D.Cost of the project.
E.None of the above.
开始考试点击查看答案 - 3Using the problem stated in the Special window, Calculate the deviation of duration for the task, using the PERT concept of standard deviation of task duration.
A.0.5
B.1
C.1.8
D.2.2
E.2.8
开始考试点击查看答案 - 4In crashing a task, you would focus on:
A.As many tasks as possible.
B.Non critical tasks.
C.Accelerating performance of tasks on critical path.
D.Accelerate performance by minimizing cost.
E.A and D.
开始考试点击查看答案 - 5Using the problem stated in the Special window, Calculate the expected value of duration (in days) using the PERT concept of the expected duration of a task
A.8
B.8.8
C.9.1
D.9.7
E.10.5
开始考试点击查看答案
最新试卷
房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它