which type of process involves the agency holding discussions with each of the offerors, after receipt of their proposals, in the process ofarriving at an agreement prior to the award of a contract、
A.sealed bidding
B.competitive proposals
C.noncompetitive proposals
D.formal bid
E.verbal bid
试卷相关题目
- 1which of the following factors has historically been the greatest contributor to project failure、
A.planning performed by a planning group.
B.poor financial estimates.
C.lack of sufficient management reserve.
D.lack of management support.
E.not using an automated tracking tool.
开始考试点击查看答案 - 2the purpose of project risk management is to:
A.identify those factors that will adversely impact project objectives.
B.assess the impact of adverse project factors.
C.assess the probability of adverse project factors.
D.a and c
E.all of the above.
开始考试点击查看答案 - 3risk can be divided into two basic types; business risk and pure (or insurable risk). of the following, which one(s) fall(s) under business risk、
A.liability loss
B.direct property loss
C.profit loss
D.personnel-related loss
E.b and c
开始考试点击查看答案 - 4once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the network. this willprovide information on the ( ) and identification of the ( ) .
A.slack for each activity, critical path.
B.slack for each activity, high risk activities.
C.manpower shortages, high risk activities.
D.high risk activities, non-critical paths.
E.manpower availability, contingency plans.
开始考试点击查看答案 - 5during a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12%of the work scheduled to this point of time. you can therefore conclude that:
A.the project will be completed late.
B.the critical path has been lengthened.
C.the costs are being overrun.
D.C.the costs are being overrun.D.overtime will be required to maintain the original critical path.
E.none of the above.
开始考试点击查看答案 - 6a non-critical path activity is completed in half the time. then,
A.the critical path is also reduced.
B.the slack in the path containing this activity will increase.
C.the total cost for this activity has decrease
D.B.the slack in the path containing this activity will increas
E.C.the total cost for this activity has decreased.D.manpower from this activity can be assigned to other activities.E.all of the above.
开始考试点击查看答案 - 7an element in the wbs was estimated to require 1 month for completion with 1000 hours of labor and a burdened cost of $50k. the task wascompleted in 1000 hours but a burdened cost of $60k. the most likely reason for the increase would be:
A.higher salaried employees were assigned.
B.overtime was required.
C.the overhead rate increase
D.B.overtime was required.C.the overhead rate increased.D.employee salaries had increased.
E.any of the above
开始考试点击查看答案 - 8in the past, most project managers have come from ( ) fields without proper ( ) training or education in skills
A.technical; accounting/finance
B.technical; management
C.technical; psychological
D.marketing; technology-oriented
E.business; manufacturing know-how
开始考试点击查看答案 - 9the risk of not meeting project quality objectives:
A.can be minimized through continuous monitoring.
B.considered a long term risk.
C.will be reflected in the "in-service" life of the product or service.
D.b and c
E.all of the above.
开始考试点击查看答案 - 10the main player in project communication is the
A.sponsor
B.project manager
C.functional manager
D.functional team
E.all of the above.
开始考试点击查看答案
最新试卷
房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它