位置:首页 > 题库频道 > 其它分类 > 资格类其它 > 项目管理师PMP美国项目管理PMPPMP认证考试练习题(1,2)

which type of contract requires that the buyer keep the tightest labor/material cost control、

发布时间:2024-07-09

A.cost plus incentive fee

B.cost plus percentage of costs

C.cost plus fixed fee

D.firm fixed price

E.firm fixed price plus incentive

试卷相关题目

  • 1which of the following is often overlooked in achieving effective communication、

    A.speaking clearly

    B.listening

    C.interpreting

    D.maintaining eye contact

    E.manipulating the conversation

    开始考试点击查看答案
  • 2the most common types of schedules are gantt charts, milestone charts, line of balance, and:

    A.networks.

    B.time phased events.

    C.calendar integrated activities.

    D.a and c only.

    E.b and c only.

    开始考试点击查看答案
  • 3the highest degrees of project risk and uncertainty are associated with the following phase of the project:

    A.conceptual

    B.execution

    C.cut-over

    D.post project evaluation

    E.a and d only

    开始考试点击查看答案
  • 4the japanese resource management model exhibits:

    A.a cooperative spirit of goal setting.

    B.non-specialized career paths

    C.frequent changes in team assignments

    D.a theory z style of management

    E.all of the above.

    开始考试点击查看答案
  • 5management plans include all of the following except:

    A.organization of project.

    B.job descriptions.

    C.policies and procedures.

    D.linear responsibility charts.

    E.scope baseline.

    开始考试点击查看答案
  • 6a task-oriented family tree of activities is a:

    A.detailed plan.

    B.linear responsibility chart.

    C.work breakdown structure.

    D.cost account coding system.

    E.work package description.

    开始考试点击查看答案
  • 7adding 5 people to a 4 person team increases the communication channels by a factor of:

    A.2 times

    B.3 times

    C.4 times

    D.5 times

    E.6 times

    开始考试点击查看答案
  • 8cost management includes:

    A.cost estimating/forecasting.

    B.cost budgeting/cost control.

    C.cost applications.

    D.all of the abov

    E.E.a and b only.

    开始考试点击查看答案
  • 9participative management:

    A.involves the solicitation of information from all team members.

    B.assumes that members avoid work and responsibility.

    C.suggests the sharing of power and decision making.

    D.employs a theory x style of leadership.

    E.a and c

    开始考试点击查看答案
  • 10the auditing function that provides feedback about the quality of output is referred to as:

    A.quality control.

    B.quality planning.

    C.quality assurance.

    D.quality improvement

    E.all of the above.

    开始考试点击查看答案