位置:首页 > 题库频道 > 其它分类 > 计算机其它 > 专业技术高级资格信息系统项目管理师综合知识2009年下半年信息系统项目管理师上午试卷

● The creation of a work breakdown structure WBS)is the process of 75)the major project deliverables.

发布时间:2024-07-09

A.subdividing

B.assessing

C.planning

D.integrating

试卷相关题目

  • 1● The Unified Modeling Language is a standard graphical language for modeling object-orientedsoftware.(74)can show the behavior of systems in terms of how objects interact with each other.

    A.Class diagram

    B.Component diagram

    C.Sequence diagram

    D.Use case diagram

    开始考试点击查看答案
  • 2● (73)is a property of object-oriented software by which an abstract operation may be performed indifferent ways in different classes.

    A.Method

    B.Polymorphism

    C.Inheritance

    D.Encapsulation

    开始考试点击查看答案
  • 3● The strategies for handling risk comprise of two main types:negative risks, and positive risks. Thegoal of the plan is to minimize threats and maximize opportunities.When dealing with negative risks,there are three main response strategies (72),Transfer ,Mitigate .

    A.Challenge

    B.Exploit

    C.Avoid

    D.Enhance

    开始考试点击查看答案
  • 4● The (71) process ascertains which risks have the potential of affecting the project and documentingthe risks' characteristics.

    A.Risk Identification

    B.Quantitative Risk Analysis

    C.Qualitative Risk Analysis

    D.Risk Monitoring and Control

    开始考试点击查看答案
  • 5● 根据企业内外环境的分析,运用SWOT配比技术就可以提出不同的企业战略。S-T战略是(70)。

    A.发挥优势、利用机会

    B.利用机会、克服弱点

    C.利用优势、回避威胁

    D.减小弱点、回避威胁

    开始考试点击查看答案
返回顶部