位置:首页 > 题库频道 > 其它分类 > 计算机其它 > 专业技术高级资格信息系统项目管理师综合知识2005年11月份信息系统项目管理师上午试题

● __(75)__ involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance. These other projects can be within the performing organization or outside of it, and can be within the same or in another application are

发布时间:2024-07-09

A.A.Metrics

B.Measurement

C.Benchmarking

D.Baseline

试卷相关题目

  • 1● __(74)__ is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.

    A.Planned value

    B.Earned value

    C.Actual cost

    D.Cost variance

    开始考试点击查看答案
  • 2● PDM includes four types of dependencies or precedence relationships:...__(73)__. The completion of the successor activity depends upon the initiation of the predecessor activity.

    A.Finish-to-Start

    B.Finish-to-Finish

    C.Start-to-Start

    D.Start-to-Finish

    开始考试点击查看答案
  • 3● The process of __(72)__ schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.

    A.estimating

    B.defining

    C.planning

    D.sequencing

    开始考试点击查看答案
  • 4● The __(71)__ describes, in detail, the project’s deliverables and the work required to create those deliverables.

    A.project scope statement

    B.project requirement

    C.project charter

    D.product specification

    开始考试点击查看答案
  • 5● The __(70)__ provides the project manager with the authority to apply organizational resources to project activities.

    A.project management plan

    B.contract

    C.project human resource plan

    D.project charter

    开始考试点击查看答案
返回顶部