位置:首页 > 题库频道 > 其它分类 > 计算机其它 > 专业技术高级资格信息系统项目管理师综合知识2005年11月份信息系统项目管理师上午试题

● The __(67)__ defines the phases that connect the beginning of a project to its end.

发布时间:2024-07-09

A.schedule

B.project life cycle

C.temporary

D.milestone

试卷相关题目

  • 1● __(66)__ means that every project has a definite beginning and a definite end.

    A.Project phase

    B.Unique

    C.Temporary

    D.Closure

    开始考试点击查看答案
  • 2● 在下列网络服务中,__(64)__是远程登录服务,Internet中域名与IP地址之间的翻译是由__(65)__来完成的。

    A.WWW

    B.FTP

    C.BBS

    D.Telnet

    开始考试点击查看答案
  • 3● 100BaseFX采用的传输介质是__(63)__。

    A.双绞线

    B.光纤

    C.无线电波

    D.同轴电缆

    开始考试点击查看答案
  • 4● 以下连网设备中,工作于网络层的设备是__(62)__。

    A.调制解调器

    B.以太网交换机

    C.集线器

    D.路由器

    开始考试点击查看答案
  • 5● 在ISO OSI/RM中,__(61)__实现数据压缩功能。

    A.应用层

    B.表示层

    C.会话层

    D.网络层

    开始考试点击查看答案
  • 6● __(68)__ are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.

    A.Project managers

    B.Project team members

    C.Sponsors

    D.Project stakeholders

    开始考试点击查看答案
  • 7● The __(69)__ Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project’s requirements.

    A.Planning

    B.Executing

    C.Monitoring and Controlling

    D.Closing

    开始考试点击查看答案
  • 8● The __(70)__ provides the project manager with the authority to apply organizational resources to project activities.

    A.project management plan

    B.contract

    C.project human resource plan

    D.project charter

    开始考试点击查看答案
  • 9● The __(71)__ describes, in detail, the project’s deliverables and the work required to create those deliverables.

    A.project scope statement

    B.project requirement

    C.project charter

    D.product specification

    开始考试点击查看答案
  • 10● The process of __(72)__ schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.

    A.estimating

    B.defining

    C.planning

    D.sequencing

    开始考试点击查看答案
返回顶部