a graphical display of accumulated costs and labor hours for both budgeted and actual costs, plotted against time, is called a(n) (    ).

发布时间:2024-07-09

A.trend line.

B.trend analysis.

C.s curve.

D.percent completion report.

E.earned value report.

试卷相关题目

  • 1which of the following types of specifications gives measurable capabilities of the product:

    A.functional specifications

    B.performance specifications

    C.conformance specifications

    D.technical specifications

    E.process capability specification

    开始考试点击查看答案
  • 2sound, prudent, but often unsophisticated judgement is called:

    A.common sense

    B.rational management

    C.smoothing

    D.confrontation

    E.none of the above

    开始考试点击查看答案
  • 3in a fishbone diagram, the effect you are concerned about is placed:

    A.at the right-hand end of the spine.

    B.at the end of the diagonal line (i.e. "fin").

    C.on a branch of a fin.

    D.at the left-hand end of the spin

    E.E.none of the above.

    开始考试点击查看答案
  • 4historical records during close-out are useful to (    ) and (    ) for future projects.

    A.predict trends, highlight problems.

    B.analyze successes, shortfalls.

    C.analyze strengths, document results.

    D.support litigation, defend claims.

    E.justify results, set standards.

    开始考试点击查看答案
  • 5a project manager who allows the team to make the majority of the decisions is demonstrating a(n) (    ) leadership style.

    A.laissez-faire

    B.boss-centered

    C.subordinate centered

    D.autocratic

    E.demographic

    开始考试点击查看答案
  • 6by using project risk management techniques, project managers can develop strategies that do all but which of the following:

    A.significantly reduce project risks

    B.eliminate project risks

    C.provide a rational basis for better decision making

    D.identify risks, their impact(s), and any appropriate responses

    E.none of the above.

    开始考试点击查看答案
  • 7in a flowchart, the diamond form is used to represent:

    A.a starting point.

    B.an operation.

    C.a written report.

    D.a decision point.

    E.an end point.

    开始考试点击查看答案
  • 8in small companies, project managers and line managers are:

    A.never the same person

    B.always the same person

    C.sometimes the same person

    D.always in disagreement with each other

    E.forced to act as their own sponsors

    开始考试点击查看答案
  • 9make or buy decisions are usually made during the (    ) phase of a project.

    A.conceptual

    B.development.

    C.implementation

    D.execution

    E.close-out

    开始考试点击查看答案
  • 10managers who adopt a sound, but prudent managerial style are called

    A.authorization

    B.conciliatory

    C.ethical

    D.judicial

    E.promotional

    开始考试点击查看答案