which of the following types of contracts allows the owner to transfer risk to the contractor:

发布时间:2024-07-09

A.cost plus incentive fee

B.cost sharing

C.firm fixed price

D.cost plus fixed fee

E.performance guarantees

试卷相关题目

  • 1which of the following is least likely to be used in explaining to a team member why you consider his/her performance substandard、

    A.project office memo

    B.counseling session

    C.project team meeting

    D.formal letter

    E.individual conversation

    开始考试点击查看答案
  • 2which of the following diagrams is most useful in impact analysis:

    A.arrow diagrams

    B.precedence diagrams

    C.decision trees

    D.pareto diagrams

    E.cause and effects diagrams

    开始考试点击查看答案
  • 3the majority of product defects could be prevented in most processes if manufactures would do the following:

    A.increase the use of acceptance control charts instead of standard three-sigma control charts.

    B.make a concerted effort to eliminate the potential for product defects in the design stage.

    C.create a quality control department.

    D.a and b

    E.a and c

    开始考试点击查看答案
  • 4the major difference between pert and cpm networks is:

    A.pert requires three time estimates whereas cpm requires one time estimate.

    B.pert is used for construction projects whereas cpm is used for r & d

    C.pert addresses only time whereas cpm also includes cost and resource availability.

    D.pert requires computer solutions whereas cpm is a manual techniqu

    E.E.pert is measured in days whereas cpm uses weeks or months.

    开始考试点击查看答案
  • 5r & d project managers in high-tech companies most often motivate using (    ) power.

    A.expert

    B.reward

    C.referent

    D.identification

    E.none of the above

    开始考试点击查看答案
  • 6a contractor estimates that a project has a 0.5 probability of $200,000 profit and 0.3 probability of $50,000 loss. the expected monetary value of this project is:

    A.200000

    B.150000

    C.85000

    D.50000

    E.none of the above.

    开始考试点击查看答案
  • 7a project manager who allows the team to make the majority of the decisions is demonstrating a(n) (    ) leadership style.

    A.laissez-faire

    B.boss-centered

    C.subordinate centered

    D.autocratic

    E.demographic

    开始考试点击查看答案
  • 8historical records during close-out are useful to (    ) and (    ) for future projects.

    A.predict trends, highlight problems.

    B.analyze successes, shortfalls.

    C.analyze strengths, document results.

    D.support litigation, defend claims.

    E.justify results, set standards.

    开始考试点击查看答案
  • 9in a fishbone diagram, the effect you are concerned about is placed:

    A.at the right-hand end of the spine.

    B.at the end of the diagonal line (i.e. "fin").

    C.on a branch of a fin.

    D.at the left-hand end of the spin

    E.E.none of the above.

    开始考试点击查看答案
  • 10sound, prudent, but often unsophisticated judgement is called:

    A.common sense

    B.rational management

    C.smoothing

    D.confrontation

    E.none of the above

    开始考试点击查看答案