the most precise or accurate estimate for determining project costs is the (    ) estimate.

发布时间:2024-07-09

A.definitive.

B.analogy

C.budget

D.modified standards.

E.rule of thumb.

试卷相关题目

  • 1smoothing out resource requirements from period to period is called resource (    ).

    A.allocation.

    B.partitioning

    C.leveling.

    D.quantification

    E.none of above.

    开始考试点击查看答案
  • 2one of your project team members has made a technological breakthrough on an r & d project. the result will be new business for thecompany, as well as a company patent. the team member received a company bonus. the motivational strategy used here is:

    A.job enrichment

    B.linking pay and performance

    C.behavior modification

    D.freedom in the work place

    E.all of the above

    开始考试点击查看答案
  • 3affinity diagrams are used to:

    A.determine if a process is in control.

    B.determine root cause.

    C.show the relationship among variables.

    D.categorize large amounts of data.

    E.none of the above.

    开始考试点击查看答案
  • 4which quality management tool would be used to determine potential causes of a production problem、

    A.control chart.

    B.ishikawa diagram.

    C.scatter diagram.

    D.histogram.

    E.run chart.

    开始考试点击查看答案
  • 5statistical cost estimating techniques (based upon history), are called (    ) estimates and are a (    ) approach.

    A.definitive, bottom up.

    B.analogy, top down.

    C.parametric, bottom up.

    D.parametric, top down.

    E.analogy, bottom up.

    开始考试点击查看答案
  • 6when subordinates know pertinent information that is not known by the project manager, the result is:

    A.blindspot

    B.facade

    C.region of influence

    D.communication power base

    E.none of the above

    开始考试点击查看答案
  • 7which of the following scheduling methods uses more of the risk management concepts:

    A.adm

    B.pdm

    C.cpm

    D.pert

    E.gantt

    开始考试点击查看答案
  • 8which of the following terms refers to the situation where the work is being used for the purpose intended and so certified:

    A.beneficial completion

    B.substantial completion

    C.project completion

    D.contract closeout

    E.final completion

    开始考试点击查看答案
  • 9a (    ) estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%).

    A.parametric

    B.definitive.

    C.budget

    D.bottom up.

    E.top down.

    开始考试点击查看答案
  • 10assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource (    ).

    A.allocation.

    B.partitioning

    C.leveling

    D.quantification.

    E.none of above.

    开始考试点击查看答案