位置:首页 > 题库频道 > 其它分类 > 资格类其它 > 项目管理师PMP美国项目管理PMPPMP认证考试练习题(3.4)

project management has been proven to be successful because employees get to see the entire effort, from beginning to end, rather than justsmall pieces. this could be considered an example of:

发布时间:2024-07-09

A.behavioral modification

B.linking performance to pay

C.positive job reinforcement

D.job enrichment

E.all of the above

试卷相关题目

  • 1management reserve is generally intended to be used to:

    A.implement additional unbudgeted scope

    B.compensate for inaccurate estimates

    C.cover major unforeseen catastrophes

    D.cover unforeseen problems in the project

    E.all of the above.

    开始考试点击查看答案
  • 2in the arrow diagramming method (adm), (    ) do not consume time or resources.

    A.events.

    B.activities

    C.slack elements.

    D.b and c only.

    E.all of the above.

    开始考试点击查看答案
  • 3assignable cause or special variation is:

    A.is indicated when a point falls outside the control limits.

    B.is indicated when a point falls outside the specification limits.

    C.is indicated when a run of seven or more points fall above the center line of a standard control chart.

    D.is indicated when a run of seven or more points fall below the center line of a standard control chart.

    E.a, c, and d

    开始考试点击查看答案
  • 4which of the following is most closely associated with pure risk:

    A.profit and loss

    B.personnel turnover

    C.insurance

    D.market fluctuations

    E.a and d only

    开始考试点击查看答案
  • 5which of the following is an element of procurement management:

    A.inspection

    B.purchasing

    C.estimating

    D.expediting

    E.a, b and d only

    开始考试点击查看答案
  • 6project managers that are available to answer questions, provide guidance when need, and generally do not interfere with day-to-day activitieshave a(n) (    ) managerial style.

    A.autocratic

    B.conciliatory

    C.ethical

    D.facilitative

    E.judicial

    开始考试点击查看答案
  • 7the scope baseline once established and approved, is used:

    A.as the basis for making future decisions.

    B.to accomplish verification measures.

    C.to evaluate potential changes.

    D.all of the abov

    E.E.a and c only.

    开始考试点击查看答案
  • 8the three most common types of project cost estimates are:

    A.order of magnitude, parametric, and budget.

    B.parametric, definitive and top down.

    C.order of magnitude, definitive and bottom up.

    D.order of magnitude, budget and definitiv

    E.E.analogy, parametric and top down.

    开始考试点击查看答案
  • 9to calculate the expected value of an outcome:

    A.divide the value of each outcome by its probability, then add the results.

    B.divide the value of the desired outcome by the value all possible outcomes

    C.multiply the value of each outcome by its probability, then add the results

    D.use linear regression to assess the expected value of the outcome

    E.b and d only

    开始考试点击查看答案
  • 10activities with zero time duration are referred to as:

    A.critical path activites.

    B.noncritical path activities.

    C.slack time activities.

    D.dummies

    E.none of above.

    开始考试点击查看答案
返回顶部