in a matrix organizational form, which factor(s) make it difficult for a project manager to provide a valid input into the employee's performancereview、

发布时间:2024-07-09

A.not working directly with the assigned functional employees

B.employees spend only a short amount of time assigned to the project

C.not being knowledgeable enough to evaluate employees on technical judgment

D.all of the above

E.a and b only

试卷相关题目

  • 1a contract originated bilaterally may be developed by (    ) .

    A.quotation request from suppliers

    B.proposal request

    C.bid invitation release

    D.b and c

    E.all of the above.

    开始考试点击查看答案
  • 2a gantt chart is useful in determining:

    A.the level of effort for a task

    B.when a task starts and stops

    C.how tasks are related to each other

    D.who is assigned to do a task

    E.all of the above.

    开始考试点击查看答案
  • 3"paraphrasing" is most closely associated with which part of the communication process、

    A.encoding

    B.decoding

    C.barriers

    D.feedback

    E.none of the above.

    开始考试点击查看答案
  • 4the difference between the bcws and the bcwp is referred to as the:

    A.schedule variance

    B.cost variance.

    C.estimate of completion

    D.actual cost of the work performed

    E.none of the above

    开始考试点击查看答案
  • 5the behavioral responsibilities of a project manager may also include dealing with:

    A.the public

    B.regulatory personnel

    C.the legal environment

    D.environmental issues

    E.all of the above

    开始考试点击查看答案
  • 6upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project arereferred to as the:

    A.baseline costs

    B.budgeted costs.

    C.estimates upon completion costs

    D.scheduled costs

    E.none of the above

    开始考试点击查看答案
  • 7which of the following is not a definition to determine a product's ability to operate as intended、

    A.distance

    B.performance

    C.function

    D.condition

    E.all are definitions

    开始考试点击查看答案
  • 8a work breakdown structure is most useful for:

    A.identifying individual tasks for a project

    B.scheduling the start of tasks

    C.developing a cost estimate

    D.determining potential delays

    E.a and c

    开始考试点击查看答案
  • 9reaching an understanding of concessions is accomplished in the (    ) stage of negotiations.

    A.protocol

    B.probing

    C.scratch bargaining

    D.closure

    E.agreement

    开始考试点击查看答案
  • 10the primary consideration of product management is to know the (    ).

    A.probability of product's performance with specified parameters

    B.ability the product has to perform its intended function

    C.ability of a product to be produced within existing parameters

    D.functionality the product will provide over its useful life

    E.all of the above

    开始考试点击查看答案