project managers must know:

发布时间:2024-07-09

A.what kind of message to send

B.to whom to send the message

C.how to translate the message into a language that everyone can understand

D.all of the above

E.a and b only

试卷相关题目

  • 1feasibility studies occur in which life cycle phase (s)、

    A.conceptual

    B.conceptual or development

    C.execution

    D.preliminary planning

    E.any life cycle phase

    开始考试点击查看答案
  • 2douglas mcgregor's theory y advocates that the average worker:

    A.dislikes work and avoids it whenever possible

    B.must be closely supervised and even threatened with punishment

    C.avoids increased responsibility

    D.wants self-respect

    E.none of the above

    开始考试点击查看答案
  • 3by which means is a contractor able to control cost overruns due to changing requirements、

    A.project data review

    B.change order

    C.purchase order amendment

    D.change control

    E.none of the above.

    开始考试点击查看答案
  • 4(    ) is a formal invitation containing a scope of work which seeks a formal response (proposal) describing both methodology andcompensation to form the basis of a contract.

    A.request for proposal

    B.invitation to bid

    C.request for quotation

    D.intention for bid

    E.none of the above.

    开始考试点击查看答案
  • 5which of the following is not a measure of the profitability of a project or program、

    A.return on original investment.

    B.net present value.

    C.depreciation.

    D.discounted cash flow.

    E.none of the above

    开始考试点击查看答案
  • 6quality attributes

    A.are used to determine how effectively the organization accomplishes its goals

    B.can be objective or subjective in nature

    C.are specific quality characteristics for which a product is designed, built, and teste

    D.D.a and b

    E.b and c

    开始考试点击查看答案
  • 7risk event probability is defined as:

    A.the total number of possible events divided into the expectations or frequency of the risk event

    B.the number of times the risk event may occur

    C.the fraction of the total project tasks which may be affected by the risk event

    D.the total number of possible events divided into the consequences of the risk event.

    E.a and b

    开始考试点击查看答案
  • 8scheduling systems such as pert, adm, and pdm are project management tools to be used by:

    A.the project manager and project office personnel.

    B.the project team and functional managers.

    C.the project sponsor.

    D.all of the abov

    E.E.a and b only.

    开始考试点击查看答案
  • 9the planned cost for the total project at its inception is called the (    ).

    A.cost of goods sold.

    B.depreciable value.

    C.budgeted cost.

    D.B.depreciable valu

    E.C.budgeted cost.D.all of the above.E.b and c only.

    开始考试点击查看答案
  • 10a process characteristic has a true mean of 150 and a true standard deviation of 20. a sample of 25 items is taken from this process. thestandard error of the estimate is:

    A.0.2

    B.0.8

    C.4

    D.5

    E.7.5

    开始考试点击查看答案