a proven effective means to insure quality conformance is to:

发布时间:2024-07-09

A.delegate accountability to subordinates

B.revise quality specifications to match quality measurements

C.train workers in proper quality methods

D.inspect quality into the product

E.make quality a higher priority than cost or schedule

试卷相关题目

  • 1(    ) is a method of procurement where a contract results from a bid which may be changed through bargaining.

    A.acquisition

    B.contract negotiation

    C.procurement

    D.purchase negotiation

    E.none of the above.

    开始考试点击查看答案
  • 2what is the relative priority of project cost, schedule and quality、

    A.1)cost - 2)schedule - 3)quality

    B.1)quality - 2)schedule - 3)cost

    C.1)quality - 2)cost - 3)schedule

    D.1)schedule - 2)quality - 3)cost

    E.all are of equal priority

    开始考试点击查看答案
  • 3to determine whether or not the employee correctly understands the message, the project manager needs to:

    A.reduce the filtering

    B.eliminate barriers

    C.obtain feedback

    D.use more than one medium

    E.use all of the above.

    开始考试点击查看答案
  • 4the project manager must be concerned with building a closely knit team. during the project kickoff meeting, the project manager can get agood start at team building by providing the team with:

    A.proposed salary increases if the project is successful

    B.bonuses for early completion date

    C.a promise of future assignments

    D.well-defined project objectives

    E.linear responsibility charts

    开始考试点击查看答案
  • 5the budget associated with scope changes that have been approved but not planned for yet, is referred to a(n) (    ) budget.

    A.unauditable.

    B.undistributed.

    C.preauthorize

    D.C.preauthorized.D.contingency.

    E.in-process.

    开始考试点击查看答案
  • 6communication management is best described as conducting or supervising

    A.the way we listen

    B.the way we speak

    C.the way we feel

    D.the exchange of information

    E.perfect documentation activities

    开始考试点击查看答案
  • 7good project objectives must be:

    A.general rather than specific

    B.established without considering resource bounds

    C.realistic and attainable

    D.overly complex

    E.measurable, intangible and verifiable

    开始考试点击查看答案
  • 8increasing resources on the critical path activities may not always shorten the length of the project because:

    A.certain activities are time-dependent rather than resource-dependent (i.e., using three ovens rather than one to bake a cake).

    B.safety, osha and epa may have placed restrictions on the number of people used on certain activities or in the physical location of theproject.

    C.the skill level of the added resources might not be appropriate for the activities to be performe

    D.D.adding more resources may create additional work and produce inefficiencies (i.

    E., additional people may need training and supervision.)E.all of the above.

    开始考试点击查看答案
  • 9universal characteristics of effective project managers include such skills as communication, decision-making, planning, ability to identifyproblems and:

    A.performing feasibility studies

    B.proposal preparation

    C.being close to the customer

    D.maturity

    E.none of the above are universal characteristics

    开始考试点击查看答案
  • 10which of the following is not a measure of the profitability of a project or program、

    A.return on original investment.

    B.net present value.

    C.depreciation.

    D.discounted cash flow.

    E.none of the above

    开始考试点击查看答案