researching, organizing and recording pertinent information is called:

发布时间:2024-07-09

A.alternative analysis

B.information gathering

C.configuration management

D.post project analysis

E.all of the above

试卷相关题目

  • 1in project risk management, risk response may include actions to:

    A.reduce the probability of risk events

    B.change the scope, budget, schedule or quality specifications of the project

    C.reduce the consequences or severity of impacts of a potential risk event

    D.a and c

    E.all of the above.

    开始考试点击查看答案
  • 2a line manager provides you with three estimates for his activity in your pert network. his estimates are 2 weeks optimistically, 4 weeksmost likely, and 12 weeks pessimistically. the expected time which would appear on the chart would be:

    A.4 weeks

    B.5 weeks

    C.6 weeks

    D.7 weeks

    E.none of the above.

    开始考试点击查看答案
  • 3(    ) is a narrative description of the work to be accomplished or resource to be supplied.

    A.purchase order

    B.level of effort work

    C.scope of work

    D.contract stipulation

    E.none of the above.

    开始考试点击查看答案
  • 4total project risk:

    A.should not be calculated for small projects

    B.is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during theproject.

    C.is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.

    D.a and b

    E.a and c

    开始考试点击查看答案
  • 5the quality objectives are approved in the conceptual stage of the project by the:

    A.project engineer

    B.project manager

    C.functional manager

    D.quality assurance manager

    E.project owner

    开始考试点击查看答案
  • 6the budget associated with scope changes that have been approved but not planned for yet, is referred to a(n) (    ) budget.

    A.unauditable.

    B.undistributed.

    C.preauthorize

    D.C.preauthorized.D.contingency.

    E.in-process.

    开始考试点击查看答案
  • 7the project manager must be concerned with building a closely knit team. during the project kickoff meeting, the project manager can get agood start at team building by providing the team with:

    A.proposed salary increases if the project is successful

    B.bonuses for early completion date

    C.a promise of future assignments

    D.well-defined project objectives

    E.linear responsibility charts

    开始考试点击查看答案
  • 8to determine whether or not the employee correctly understands the message, the project manager needs to:

    A.reduce the filtering

    B.eliminate barriers

    C.obtain feedback

    D.use more than one medium

    E.use all of the above.

    开始考试点击查看答案
  • 9what is the relative priority of project cost, schedule and quality、

    A.1)cost - 2)schedule - 3)quality

    B.1)quality - 2)schedule - 3)cost

    C.1)quality - 2)cost - 3)schedule

    D.1)schedule - 2)quality - 3)cost

    E.all are of equal priority

    开始考试点击查看答案
  • 10(    ) is a method of procurement where a contract results from a bid which may be changed through bargaining.

    A.acquisition

    B.contract negotiation

    C.procurement

    D.purchase negotiation

    E.none of the above.

    开始考试点击查看答案