an informal communication network on a project and within an organization is called a(n):

发布时间:2024-07-09

A.free upward flow

B.free horizontal flow

C.unrestricted communication flow

D.grapevine

E.open network

试卷相关题目

  • 1adm is an activity-on-arrow method. in this method, a dummy activity:

    A.denotes a critical path relationship.

    B.denotes any dependency relationship.

    C.shows slack.

    D.identifies customer deliverables dates.

    E.identifies customer team meeting dates.

    开始考试点击查看答案
  • 2(    ) is associated with a buyer's request for materials or equipment to meet a particular need or accomplish a specific purpose.

    A.express warranty

    B.implied warranty of merchantability

    C.implied warranty of fitness for a particular purpose

    D.prescribed warranty

    E.none of the above.

    开始考试点击查看答案
  • 3by which process may an unsuccessful supplier seek remedy for unjust awards、

    A.contract dispute

    B.stop work order

    C.bid protest

    D.coffective action

    E.none of the above.

    开始考试点击查看答案
  • 4risk classified as unknown unknowns (i.e., those which cannot be identified or evaluated):

    A.should be deflected to the contracting officer

    B.should be handled via contingency allowances

    C.should be ignored, since they cannot be identified

    D.should be ignored, since they are not covered in the project risk assessment

    E.c and d

    开始考试点击查看答案
  • 5the "zero defect" concept was proposed by:

    A.deming

    B.juran

    C.crosby

    D.tagushi

    E.a and d only

    开始考试点击查看答案
  • 6the major difference between project and line management is that the project manager may not have any control over which basicmanagement function、

    A.decision-making

    B.staffing

    C.rewarding

    D.tracking/monitoring

    E.reviewing

    开始考试点击查看答案
  • 7which of the following planning considerations is often overlooked、

    A.planning for project termination.

    B.qualified project manager assignment.

    C.insuring top management support.

    D.clearly defined tasks.

    E.all of the above.

    开始考试点击查看答案