当前位置:首页 > 全部子站 > 长理财会培训 > 国际证书考试 > ACCA

2020年ACCAF5考试主观题:有关成本的相关考题2

来源:长理培训发布时间:2020-03-11 21:04:00
【Answers】

1 Edward Limited

(a) Target costing process

Target costing begins by specifying a product an organisation wishes to sell. This will involve extensive customer analysis,

considering which features customers value and which they do not. Ideally only those features valued by customers will be

included in the product design.

The price at which the product can be sold at is then considered. This will take in to account the competitor products and

the market conditions expected at the time that the product will be launched. Hence a heavy emphasis is placed on external

analysis before any consideration is made of the internal cost of the product.

From the above price a desired margin is deducted. This can be a gross or a net margin. This leaves the cost target. An

organisation will need to meet this target if their desired margin is to be met.

Costs for the product are then calculated and compared to the cost target mentioned above.

If it appears that this cost cannot be achieved then the difference (shortfall) is called a cost gap. This gap would have to be

closed, by some form of cost reduction, if the desired margin is to be achieved.

(b) Benefits of adopting target costing

– The organisation will have an early external focus to its product development. Businesses have to compete with others

(competitors) and an early consideration of this will tend to make them more successful. Traditional approaches (by

calculating the cost and then adding a margin to get a selling price) are often far too internally driven.

– Only those features that are of value to customers will be included in the product design. Target costing at an early stage

considers carefully the product that is intended. Features that are unlikely to be valued by the customer will be excluded.

This is often insufficiently considered in cost plus methodologies.

– Cost control will begin much earlier in the process. If it is clear at the design stage that a cost gap exists then more can

be done to close it by the design team. Traditionally, cost control takes place at the ‘cost incurring’ stage, which is often

far too late to make a significant impact on a product that is too expensive to make.

– Costs per unit are often lower under a target costing environment. This enhances profitability. Target costing has been

shown to reduce product cost by between 20% and 40% depending on product and market conditions. In traditional

cost plus systems an organisation may not be fully aware of the constraints in the external environment until after the

production has started. Cost reduction at this point is much more difficult as many of the costs are ‘designed in’ to the

product.

– It is often argued that target costing reduces the time taken to get a product to market. Under traditional methodologies

there are often lengthy delays whilst a team goes ‘back to the drawing board’. Target costing, because it has an early

external focus, tends to help get things right first time and this reduces the time to market.

(c) Steps to reduce a cost gap

Review radio features

Remove features from the radio that add to cost but do not significantly add value to the product when viewed by the

customer. This should reduce cost but not the achievable selling price. This can be referred to as value engineering or value

analysis.

Team approach

Cost reduction works best when a team approach is adopted. Edward Limited should bring together members of the

marketing, design, assembly and distribution teams to allow discussion of methods to reduce costs. Open discussion and

brainstorming are useful approaches here.

Review the whole supplier chain

Each step in the supply chain should be reviewed, possibly with the aid of staff questionnaires, to identify areas of likely cost

savings. Areas which are identified by staff as being likely cost saving areas can then be focussed on by the team. For

example, the questionnaire might ask ‘are there more than five potential suppliers for this component?’ Clearly a ‘yes’ response

to this question will mean that there is the potential for tendering or price competition.

Components

Edward Limited should look at the significant costs involved in components. New suppliers could be sought or different

materials could be used. Care would be needed not to damage the perceived value of the product. Efficiency improvements

should also be possible by reducing waste or idle time that might exist. Avoid, where possible, non-standard parts in the

design.

Assembly workers

Productivity gains may be possible by changing working practices or by de-skilling the process. Automation is increasingly

common in assembly and manufacturing and Edward Limited should investigate what is possible here to reduce the costs.

The learning curve may ultimately help to close the cost gap by reducing labour costs per unit.

Clearly reducing the percentage of idle time will reduce product costs. Better management, smoother work flow and staff

incentives could all help here. Focusing on continuous improvement in production processes may help.

Overheads

Productivity increases would also help here by spreading fixed overheads over a greater number of units. Equally Edward

Limited should consider an activity based costing approach to its overhead allocation, this may reveal more favourable cost

allocations for the digital radio or ideas for reducing costs in the business.

(d) Cost per unit and cost gap calculation

Component 1 $ per unit

(4·10 +

$2,400

) 4·70 ––––––––––

4,000 units

Component 2

(

25

x 0·5 x

100 )

0·128 ––– –––

100 98

Material – other 8·10

Assembly labour

(

30

x $12·60/hr x

100 )

7·00 –– –––

60 90

Variable production overhead

(

30

x $20/hr) 10·00 ––

60

Fixed production overhead

(

30

x $12/hr) 6·00 ––

60

–––––––

Total cost 35·928

Desired cost

($44 x 0·8) 35·20

–––––––

Cost gap 0·728

–––––––

Working

1. Production overhead cost

Using a high low method

Extra overhead cost between month 1 and 2 $80,000

Extra assembly hours 4,000

Variable cost per hour $20/hr

Monthly fixed production overhead

$700,000 – (23,000 x $20/hr) $240,000

Annual fixed production overhead ($240,000 x 12) $2,880,000

FPO absorption rate

$2,880,000

= $12/hr

责编:刘希

发表评论(共0条评论)
请自觉遵守互联网相关政策法规,评论内容只代表网友观点,发表审核后显示!

国家电网校园招聘考试直播课程通关班

  • 讲师:刘萍萍 / 谢楠
  • 课时:160h
  • 价格 4580

特色双名师解密新课程高频考点,送国家电网教材讲义,助力一次通关

配套通关班送国网在线题库一套

课程专业名称
讲师
课时
查看课程

国家电网招聘考试录播视频课程

  • 讲师:崔莹莹 / 刘萍萍
  • 课时:180h
  • 价格 3580

特色解密新课程高频考点,免费学习,助力一次通关

配套全套国网视频课程免费学习

课程专业名称
讲师
课时
查看课程
在线题库
面授课程更多>>
图书商城更多>>
在线报名
  • 报考专业:
    *(必填)
  • 姓名:
    *(必填)
  • 手机号码:
    *(必填)
返回顶部